Friday, July 25, 2014

The Lot - July 18 - 25 - PROGRESS

Finally real, actual progress on the house!! Over the past 2 weeks the rough-in plumbing was done and then the foundation was poured. It took 21 loads of cement to get it done! Framing starts next week and I am SO excited to see #harrisonwhitfarmhouse come together!!

Looking from the street. On the right side is the Master bedroom, bath, closet and on the front of the house will be the flex room (movie theatre). In the middle will be the big open kitchen/dining/family room. On the left is the kids "hang out" room, their 3 bedrooms, 2 baths and the on the front left is the pantry, mudroom, utility room and 3 car garage.

Front porch. When you walk in you'll be in the foyer. To the right is the flex room, to the left will lead you past a closet, powder room and then into the K/D/F room.

Looking at the back porch. 3 sets of French door will lead out to the outside kitchen. We'll also have a fireplace and living area too! We'll be able to watch the deer on the lot!

No comments :